Analysis of risks of short-span bridge using Primavera Risk Analysis
Bandi Sri Ram Gopal, Vundi Siva Prasad Raju, Srinivasa Reddy Vempada, Meduri Venkata Seshagiri Rao, Himanshu Dhall, Manish Kumar · AIP conference proceedings · 2025
Not cached yet. This record was fetched live for this request and is stored after the lookup. Reopening the page should serve the cached copy.
AIP conference proceedings · American Institute of Physics · conference-paper · 2025
Abstract
From the beginning to the end of the bridge construction process, there are several dangers. More dangers exist in bridge construction than in other technological fields. The frequency of risk incidents might cause building enterprises to suffer substantial losses. Project failure and construction mishaps are probable if risks are not properly evaluated. Risk analysis is a method of evaluation that establishes the degree of risk involved with a project. The condition of infrastructural facilities ensures the security and prosperity of society.
Risk analysis was carried out to identify the reasons of bridge failure, and the risks were divided into three categories: design risk, construction risk, and financial risk. A questionnaire survey was used to rank different threats. The purpose of this study is to pinpoint factors that affected the bridge building project and to incorporate important standards to enhance risk evaluations. In order to analyze the risks related to a construction project, this study makes use of computer software, namely Primavera Risk Analysis, in the Risk Management Process of construction projects.
It entails creating a schedule, assigning three-dimensional time estimates, and using Primavera risk analysis to finish iterations. The Primavera Risk Analysis tool receives the prepared schedule, processes it, and outputs distribution graphs as its findings. The Yella Reddy Tank Bund Portion bridge construction project in the Nizamabad region (Hyderabad-Medak-Bodhan) was the focus of this inquiry. The analysis’s findings were anticipated to help project managers concentrate on a small number of crucial areas and achieve optimal outcomes as opposed to focusing on everything and falling short of achieving results that are proportionate.